The project comprises three phases, each with its own focus and an unforeseeable delay:
Phase I, 2006–2009
- Project planning incl. analyses
- Deeding of property
- Architectural competition
- Project loan city of Zurich
Phase II, 2009–2012
- Founding of the simple project partnership for the Kunsthaus expansion
- Increase of project loan
- Project planning and development plan
- Fundraising
- Referendum regarding project financing
Phase III, 2013–2020
- Invitations to tender
- Fundraising (continuation)
- Building permit and construction approval
- Recours: Delay of construction (two years)
- Start of the construction works 2015
- Marketing
- Initial move and launch of operations 2020